NDIC prepares list of 26 major projects for implementation in the first stage of the Action Plan

The National Development and Innovation Committee (NDIC) has collected comprehensive information and prepared preliminary estimates on 26 major projects to form part of the Government program on implementing its Action Plan. Earlier, a Government decree had asked several ministries as also the NDIC to submit to the Government before the end of 2009 a list of projects to be offered to foreign and domestic investors. Ch.Khashchuluun, NDIC Chairman, has said the aim of the exercise is to diversify the national economy and make it a multi-pillared one, as well as attract investment.


According to him, the basic NDIC criteria for selection were that the project should require a minimum investment of $200 million and should meet priority needs of economic and social development. The 26 proposals were selected after an evaluation of their impact upon exploitation of mineral resources deposits, industrialization, and infrastructure, and after considering their economic and social significance, feasibility and likelihood of implementation, and likely contribution to sustainable economic development and to the furtherance of research and production of high technology.  

The NDIC has published a list of the projects and the priority considerations behind their selection.

1.    Developing the mining sector by exploiting mineral resources deposits and setting the foundation for heavy industry: The emphasis was on large factories to process coloured and black metallurgy and petroleum.

2.    Developing intensified agriculture and implementing the industrialization policy: The emphasis was on high technology-based factories to develop cattle breeding and farming, and to supply the entire domestic demand with products that meet requirements of hygiene.   

3.    Developing infrastructure: The emphasis was on projects linked with exploiting strategic mining deposits. For example, the projects include the construction of a new railroad, increasing the present capacity of the railroad network so that transit transportation capacity also increases, establishing new power stations and constructing paved roads in rural areas.

4.    Providing sustainable development through improving human resources and protecting the environment: The emphasis was on projects on environment protection, tourism promotion, and establishment of training-production centres for information technology.

5.    Improving governance and supporting private sector: The emphasis was on supporting manufacturers in the private sector and developing public-private-partnership.

The following is the list of 26 major projects prepared by the National Development and Innovation Committee to be implemented by the Government in pursuance of a decree.

 

 

/Unofficial translation/

Annex of Government Decree N 320, 2009


LIST OF LARGE PROJECTS WITH TOP PRIORITIES TO BE
IMPLEMENTED BY THE GOVERNMENT
 

¹ Project name

Estimated cost
($ million)

Timeframe

Priority one: Developing the mining sector by exploiting mineral resources deposits and setting the foundation for heavy industry
1 Oyu Tolgoi                                    4000.0   2010-2015
2 Tavan Tolgoi project                                 800.0   2010-2015
3 Copper smelting factory                              1000.0   2010-2015
4 Metallurgy complex                                1000.0   2011-2016
5 Coke -chemical plant                               700.0   2010-2015
6 Oil refinery                                      900.0   2011-2015
7 Coal chemical and processing plant                          1000.0   2010-2015

8

Construction materials                                 800.0   2010-2015

Priority two: Developing intensified agriculture and implementing the industrialization policy
9 Hygienic food projects to make livestock healthy and increase meat and dairy production   150.0              2010-2015
10 Development of irrigation systems                  50.0  
11 Agricultural products and raw materials storage                      50.0   2010-2011
12 High-technology-based industrial complex and science parks                400.0   2010-2015

Priority three: Developing infrastructure
13 Tavan Tolgoi power station                               400.0   2010-2015
14 New railroads                                     800.0   2010-2015
15   Providing Gobi region with water from the Orkhon Rivert   540.0   2010-2015
16 National satellite for communications                           100.0   2010-2015
17 Upgrading of Ulaanbaatar roads               900.0   2010-2015
18 Development of international, national and local motorable roads   1200.0   2010-2015
19 Highway from Altanbulag – Ulaanbaatar – ZaminUud   1200.0   2010-2015
20 Power plant No. 5                                   300.0   2011-2016
21 Construction development to provide the population with accommodation   2100.0   2010-2015
22 Energy  from waste and biomass                          200.0   2010-2015

Priority four: Providing sustainable development through improving human resources and protecting the environment
23 Information technology development and training centre   100.0   2010-2015
24 Students town                                      300.0   2010-2015
25 Development of the 13th-century capital city of Kharkhorin for tourism         500.0   2010-2015
26 ECO, for treatment of polluted and used water                      200.0   2010-2015